We’re helping PowerCo secure Palmerston North’s energy supply for the future. PowerCo is delivering a number of power projects across Palmerston North as part of a five-year project to upgrade the city’s energy supply. We have been engaged to build a new 33KV substation on the corner of Linton and Fergusson Roads to house new transformers and associated switchgear information.

The award of this project is particularly exciting for Maycroft as this will be the first time we have worked with PowerCo.

Construction will commence in mid February and is expected to take six months to complete.